A 4GW data centre blackout in Northern Virginia has pushed PJM Interconnection, North America's largest grid operator, to reconsider how facilities connect to the bulk power system. For UK buyers weighing what is colocation versus owned capacity, the ripple effects on cost and resilience standards are worth watching closely.
View the data behind this chart
| July 2024 | July 2026 | |
|---|---|---|
| Load dropped from grid | MW1500 | MW4000 |
What happened in Northern Virginia
On 22 July 2026, a transmission line fault in Northern Virginia — the world's densest data centre cluster — triggered a chain reaction. Facilities in the area disconnected themselves from the grid and switched to backup power, according to Dominion Energy, the local utility. PJM says the event brought roughly 4GW of data centre load offline, the largest incident of its kind across its entire footprint, though it stopped short of causing wider reliability damage.
PJM reported that while the grid avoided a serious reliability breach, the sudden loss of load caused a sharp imbalance between generation and demand, with large swings in voltage and frequency. Data Center Knowledge separately put the load transferred to onsite generation at around 3.8GW (3,800MW), underscoring just how concentrated and fragile this corner of the US grid has become.
Why PJM is rethinking ride-through rules
PJM's operating committee has met with Dominion to review preliminary findings and is now working on standards to integrate large computational loads more reliably. The core problem, as PJM sees it, is oversensitive protection settings. Committee chair Emanuel Bernabeu put it bluntly: "These data centers are too sensitive to the kind of voltage that they like, and we feel they are disconnecting too early."
PJM's Matthew Wharton confirmed the RTO is "evaluating potential enhancements to reliability requirements, with consideration of existing and future industry ride-through standards and practices." This is not an isolated review — the US Federal Energy Regulatory Commission ordered the North American Electric Reliability Corporation in July to draft the first phase of enforceable reliability standards specifically targeting computational loads, giving the Virginia event federal regulatory weight rather than leaving it as a regional matter.
A pattern, not a one-off
This is the second major Northern Virginia load-loss event PJM has had to manage in recent years. A July 2024 incident, caused by a lightning arrestor failure on a 230kV line, saw around 1,500MW across 60 data centres drop off the grid simultaneously, forcing PJM and Dominion to rapidly cut generation to avoid a wider surge. The 2026 event was nearly triple the size. PJM has also separately been granted emergency authority to curtail large loads with backup generation during periods of tight summer reserves, framing curtailment as a last resort before rolling blackouts — a sign of how thin the regional margin has become.

The cost side: transmission spend and BTM reform
Reliability isn't the only front moving. PJM has already approved an $11.8 billion transmission expansion plan tied to data centre demand, including a line designed to deliver roughly 3GW into Loudoun County. It has separately approved $5.9 billion in additional projects supporting large loads. PJM has also asked FERC to overhaul behind-the-meter rules, proposing a 50MW threshold above which new facilities could no longer net their load against onsite generation for tariff purposes — a change that would materially raise the cost exposure of large colocated developments that currently benefit from that netting treatment.
FERC has gone further, ordering all six major US RTOs, PJM included, to justify or reform large-load interconnection rules covering co-location agreements, behind-the-meter generation, and cost-shifting. Constellation has separately asked FERC for clarity on how colocated data centre arrangements should be treated under PJM's framework, and a prior ruling on a co-located Susquehanna project found that PJM considered up to 480MW deliverable without material grid impact — but anything beyond that would require system upgrades. PJM has also flagged that data centre-driven peak load could grow by 30GW through 2030, reinforcing why both reliability and cost rules are being tightened in parallel.
What this means for UK colocation and owned-DC buyers
The UK grid is a different regulatory system, but the underlying pressure — dense compute demand outpacing available capacity and forcing tighter interconnection scrutiny — is the same pattern now playing out around Ofgem data centre grid connection fees here. Buyers assessing US colocation exposure, or benchmarking their own UK data centre power and energy strategy, should treat PJM's ride-through review as an early signal of where large-load interconnection standards are heading globally: more conditions attached to grid connection, less tolerance for facilities that disconnect at the first sign of a voltage dip, and higher costs where behind-the-meter generation is used to avoid grid charges.
Virginia regulators have already been narrowing backup-generator permissions around data centres, tightening a proposed variance down to Loudoun County alone after initially considering three counties — a reminder that local planning and environmental rules can move as fast as grid operator policy. UK buyers negotiating colocation contracts or sizing on-site backup should stress-test resilience assumptions using tools such as a downtime cost calculator and revisit power and cooling tools and UPS calculator sizing against scenarios where grid disconnection is penalised rather than rewarded.
- •Reliability standards for computational loads are moving from voluntary practice to enforceable NERC rules
- •Behind-the-meter netting benefits may shrink above a 50MW threshold in PJM's territory
- •Transmission investment ($11.8bn, $5.9bn) shows grid operators expect years of continued build-out, not a slowdown
- •Local permitting (Virginia's generator variance) can restrict backup power options as fast as federal rules change
View the data behind this chart
| Layer | Detail |
|---|---|
| FERC directive | Orders NERC to draft enforceable load standards |
| PJM/Dominion review | Joint assessment of ride-through requirements |
| NERC Phase 1 standards | First enforceable rules for computational loads |
| Behind-the-meter reform | 50MW netting threshold, three-year transition |
What to watch next
Three threads will determine how far this goes: NERC's first-phase reliability standards for computational loads, PJM's ongoing joint review with Dominion of ride-through requirements, and FERC's decisions on PJM's behind-the-meter and large-load interconnection reforms. Any of these could shift the economics of US colocation leases and owned-facility builds materially, and buyers should factor that uncertainty into procurement timing rather than assuming current interconnection terms will hold.
- 01DataCenterDynamics — PJM considering changes to interconnection reliability requirements for data centers following mass outage · 13 August 2026
- 02Data Center Knowledge — 3.8 GW Load Drop Prompts Potential PJM Data Center Rules · 13 August 2026
- 03DataCenterDynamics — Virginia narrowly avoided power cuts when 60 data centers dropped off the grid at once · 1 August 2024
- 04DataCenterDynamics — PJM granted emergency approval to curtail data centers due to hot weather concerns · 1 May 2026
- 05DataCenterDynamics — Virginia environment dept removes Fairfax and Prince William from proposals to relax generator restrictions · 1 January 2025
- 06DataCenterDynamics — PJM approves $11.8bn transmission expansion plan amid data center boom · 1 June 2025
- 07DataCenterDynamics — PJM requests approval from FERC for new behind-the-meter generation rules for data centers · 1 July 2025
- 08DataCenterDynamics — FERC orders US grid operators to justify or reform how data centers connect to the grid · 1 March 2025
- 09DataCenterDynamics — PJM reports peak load growth of 30GW through 2030 from the data center sector · 1 January 2025
- 10DataCenterDynamics — PJM approves $5.9bn in new transmission projects to support data centers · 1 December 2024
- 11The Register — Regulators reject power deal for nuclear Amazon datacenters · 4 November 2024
- 12DataCenterDynamics — Constellation files complaint to FERC requesting clarity on PJM rules for colocated data centers · 1 February 2025
